We have been advised of upgrades to the wastewater network in Newtown and Burghclere near Sheepwash Lane from 2 March 2025 onwards. This work involves replacing approximately 950m of ageing wastewater pipes using open-cut excavation, starting from the junction of Ox Drove and progressing along Well Street.
Key Project Highlights:
• Start Date: 2 March 2025
• Phase 1 Duration: TBC, subject to site conditions (anticipated to last 3-4 weeks)
• Future Phases: Residents and businesses will be notified via post as each new phase of work begins.
• Full Project Completion: Expected by 30 June 2025 (subject to change based on site progress).
• Traffic Management: Full road closures on Well Street with signposted diversions (Sheepwash Lane remains open during Phase 1).
Pedestrian access will be maintained for residents along with access for emergency vehicles. Wastewater service will not be affected during the works.
The full notification can be found here: Sheepwash Lane SPS-Letter-Of-Notice